DDC Doda reviews implementation of CSS of PDD sector

04/12/2019

DODA, DEC 3: District Development Commissioner, Dr Sagar D Doifode convened a meeting to review the progress of PDD sector under various CSS schemes in the district.
DDC was apprised by the concerned officer that as per the scope of various schemes of rural electrification in total 600 poles have been erected in 20 habitations. He was further informed that 6000 poles have been already dumped, 312 transformers of different capacities have to be install, installation of 03 receiving stations against which survey of receiving station Gundna stands conducted. DDC directed the site engineer of executing agency to complete the erection of 6000 poles within one month, besides directed for 100% dumping of material required for the completion of works in these habitations.
While reviewing the progress of urban electrification under IPDS, PMDP (urban), the concerned executing agency informed that 200 poles have been erected, 10 transformers of different capacities have been installed at the required locations, installation of 02 receiving stations of (10MVA) and 1 km cabling have been laid down in Doda and Bhaderwah.
The DDC directed the concerned company to ensure the dumping of all poles within 15 days and complete the remaining cabling within two months, besides directs the erection of all poles within 45 days.
He also directed the ACR Doda Kaiser Ahmed Bhawani and HQA Daljeet Singh Parihar to resolve ROW issue if any in laying of new 33 KV line from Khaleni to Doda envisaged under the scheme.